Do you need planning permission for air conditioning?
Usually not. Here is when you do.
In England, most homes do not need planning permission for air conditioning. Since May 2025, a system that heats as well as cools counts as permitted development, as long as the outdoor unit is no larger than 1.5 m³ and it passes the MCS 020a noise check.
When you do not need permission.
Permitted development for air source heat pumps on homes in England (Class G, Part 14 of the General Permitted Development Order, as amended in 2025).
- The system must heat, or heat and cool. Cooling-only units are not covered.
- The outdoor unit, including any housing, must be no larger than 1.5 m³ on a house, or 0.6 m³ on a block of flats.
- It must meet the MCS 020a noise standard: no more than 37 dB(A) at the nearest neighbour's window.
- One unit per house, or up to two on a detached house.
- Not on a pitched roof. On a flat roof, it must be at least 1 m from the edge.
- Not where a wind turbine is already installed.
- Sited, as far as practicable, to limit its effect on how the building and area look, and removed when no longer needed.
When you will need it.
- Listed buildings, which usually need listed building consent too
- Conservation areas, where the unit faces a road or sits closer to the road than the house
- Business premises, which are not covered by the home rights
- Outdoor units larger than the size limits, or more units than allowed
- Installations that fail the MCS 020a noise calculation
- Cooling-only systems
What changed in 2025.
Before May 2025, permitted development only covered heat pumps used for heating, so most air conditioning needed a conversation with the council. The 2025 amendment extended the rights to systems that heat and cool, which covers modern reverse-cycle air conditioning.
It also scrapped the rule that units had to be at least 1 m from the boundary, raised the size limit for houses from 0.6 m³ to 1.5 m³, and allowed two units on detached houses.
We check before we fit.
On survey we check your property against these rules, choose a position for the outdoor unit that keeps it quiet and discreet, and tell you plainly if anything needs an application. Send us your postcode and a photo of where you would like the unit, and we will tell you where you stand.
This guide covers England. Wales and Scotland have their own rules. It is general guidance, not legal advice. If in doubt, your local planning authority can confirm.
Questions, answered.
Do I need planning permission for air conditioning in England?
Usually not for a home. Since May 2025, an air conditioning system that also heats (an air-to-air heat pump) is permitted development on a house in England, provided the outdoor unit is no larger than 1.5 m³, it meets the MCS 020a noise standard, and it is not on a listed building or a pitched roof.
Do I need planning permission for air conditioning in a conservation area?
Only in certain positions. In a conservation area the outdoor unit is not permitted development if it is on a wall or roof facing a road, or closer to the road than the house itself. Sited at the side or back, it can usually go ahead without an application.
Do I need planning permission for air conditioning in a flat?
A unit on a block of flats can be permitted development if the outdoor unit is no larger than 0.6 m³ and only one is installed on the building. You will almost always also need written permission from the freeholder or management company under your lease.
Do I need planning permission for air conditioning on a listed building?
Yes. Permitted development rights do not apply to listed buildings, so you will need planning permission and usually listed building consent as well.
Do I need planning permission for commercial air conditioning?
Often, yes. The permitted development rights for heat pumps only cover homes and blocks of flats. Whether a shop, office or restaurant needs permission depends on the building, the equipment and the location, so check with your local planning authority. We can help with the information they ask for.
Do I need permission for cooling-only air conditioning?
Cooling-only systems are not covered by the heat pump permitted development rights, so check with your council. Every system we install heats as well as cools, so this rarely applies to our customers.
Not sure? Just ask.